Oncor Electric Delivery plans a roughly 20% expansion in its five-year Texas grid construction due to rising data center power requests, raising concerns about infrastructure costs if many projects do not materialize. ERCOT and regulators are conducting careful reviews to separate real demand from speculative data center load, with a significant transmission upgrade approved in Texas amid land and cost disputes.
This Wire brief sits within Fusion42's coverage of Telecom & Connectivity.
◆ ◆ The Wire takeaway
You face rising infrastructure costs as Texas data center power requests inflate grid expansion plans. Reviewing projects ERCOT flags as firm will protect you from chasing speculative demand and overbuilding.