Wire · technology
FERC rejects most of PJM's large load interconnection plan
◆ Sectors
Clean Energy
◆ Geography
United States
◆ Source
◆ Verified
Fusion42 · 13 October 2026 · Fusion42 review
The Federal Energy Regulatory Commission (FERC) rejected most of PJM Interconnection's plan to curtail large electricity loads without matching new generation because it infringes on state jurisdiction and may be discriminatory.
This Wire brief sits within Fusion42's coverage of Clean Energy.
◆ ◆ The Wire takeaway
FERC's rejection opens regulatory uncertainty for PJM's large load customers and operators. You should engage state regulators and review your interconnection contracts to avoid sudden curtailments or penalties.
◆ Coverage
1 source · 12 Oct 2026
◆ Related on Wire
◆ Topics
Clean Energyelectricity-gridregulationFERCPJMload-management